Eskom has announced that it will implement Stage 2 loadshedding from 11:00am on Wednesday, 02 February 2022 until 05:00am on Monday, 07 February 2022.
The power utility says this is due to a shortage of generation capacity following breakdowns of two more generating units during the night.
Per the published statement:
Eskom regrets to inform the public that Stage 2 loadshedding will be implemented from 11:00 this morning until 05:00 on Monday. This loadshedding is necessary due to a shortage of generation capacity following breakdowns of two more generating units during the night.
Since the weekend Eskom has utilised significant amounts of emergency generating reserves, which have now been depleted and need to be replenished. Eskom will use this period of loadshedding to replenish the emergency generation reserves.
A unit each at Kusile and Kendal power stations tripped. Delays in returning units at Kusile, Tutuka,
Duvha, Lethabo and Grootvlei have also contributed to the current supply constraints.Total breakdowns amount to 14 994MW while planned maintenance is 4 435MW of capacity as we continue with the reliability maintenance. Three generating units are expected to return to service by this afternoon.
In the meantime, Eskom is urging the public to reduce the usage of electricity.